The project consists of four substations located at New Cairo, Beni Suef, East Ismailia, and Mansoura over a total land area of 96,375 m2.
Each substation consists of the following components: gantry area, control building, 220 KV GIS building, 66 KV switchgear building, MV switchgear building, 40 MVA transformer building, 175 MVA transformer building, firefighting building, guard room, utility buildings & services, and water tanks.
ECG’s scope of work covers detailed design and shop drawings.