Softner Manufacturing Plant

Project Description

The purpose of this project was to construct a new softener manufacturing facility on an area of approximately 5,500 m2 within the existing plant. The project houses all the facilities required for the planned production including:
• Making Building: one-storey high, air conditioned, steel-structured space divided into few separated functional spaces for batch making system, raw material staging, buffer tanks and workshop.
• Packing building: one-storey high, air conditioned, steel-structured space divided into few separated functional spaces for packing and warehouse.
• Utilities building: two levels, subject to future expansion up to four levels including transformers in the ground floor, ring main unit and medium & low
voltage panels in the first floor, compressed air unit in the second floor, and chillers & cooling towers on the roof.
• Administration building: two levels, subject to future expansion up to 4 levels including IT room, Quality Assurance labs, 2 meeting rooms that could be converted to one larger room, 2 huddle rooms, breakout area, toilets (for 20 permanent workers), and office spaces accomodating 15 persons.
• Tank farm, which has reinforced concrete foundation to support the tanks. ECG used Revit BIM Package throughout the design process.

Activities

  • Architectural
  • Communications and security systems
  • Electrical
  • HVAC
  • Interior Design
  • Mechanical
  • Structural

Scope

  • Construction supervision
  • Design development
  • Detailed design
  • Shop drawings

Client

Confidential

LOCATION

egypt

,

6th-of-october-city

,

project sheet

Download File (pdf 1150KB)